How to Streamline the RFQ Process for Spare Parts: Step-by-Step Guide and Template

Automa.Net
Automa.Net
|Published:|12 min read

The RFQ Workflow for Spare Parts in Six Steps

A streamlined RFQ workflow for industrial spare parts has six steps: confirm the exact part, write a request a supplier can quote in one pass, pick the right number of suppliers, send it with a hard deadline, compare the quotes like-for-like, and record the result so the next request starts from data. An RFQ (request for quotation) is a written request asking suppliers for a binding price, availability and terms for a defined item. Most slow RFQ cycles come from ambiguous requests, the wrong suppliers or quotes nobody can compare, not from slow suppliers.

  1. Identify the part down to order code, revision and firmware.
  2. Write the RFQ with part number, revision, condition, quantity, certificates and deadline.
  3. Choose suppliers by part type and availability, not by habit.
  4. Send and manage questions so every supplier gets the same information.
  5. Compare quotes like-for-like after normalising condition, lead time, warranty and delivery terms.
  6. Award and record the outcome against the material number.

If you are choosing a tool to run this process, our comparison of RFQ management software covers that separately.

Step 1: Confirm the Exact Part Before You Ask for a Price

Procurement manager reviewing bill of materials data at desk with dual monitors displaying inventory records and supplier information in organized spreadsheet format

The fastest way to shorten an RFQ cycle is to remove every question a supplier would otherwise send back. That starts with knowing exactly what you are buying.

A material master entry like "PLC CPU Siemens" is not a part. The full order code is. For automation parts the suffix matters: two drives with the same base number can differ in voltage, braking chopper, communication card or firmware family. When the material master is incomplete, read the nameplate on the installed unit or the spare on the shelf. A nameplate photo identification tool such as Automa.Net's AutomaSnap turns a photo of the label into a part number you can put in the request.

Before the RFQ goes out, check four things:

  • Full order code, including every suffix, not a shortened catalogue number.
  • Hardware revision and firmware version where the replacement must match a running configuration or a backup project.
  • Lifecycle status. If the part is discontinued, decide whether you will accept the successor and state it. Our guide on how to source obsolete industrial parts covers the successor question in detail.
  • Duplicates in your own stores. The same part under two material numbers means you may already have it in stock, or you send two RFQs for one need. Cleaning the bill of materials before a large sourcing round prevents both.

Step 2: Write an RFQ Suppliers Can Quote in One Pass

A complete RFQ for spare parts states the part, the revision, the acceptable condition, the quantity, the documents you need and the deadline, so a supplier can quote without asking anything. Each missing field costs at least one email round trip.

Condition: The Field Most RFQs Leave Out

Condition is the single biggest reason quotes for the same part number are not comparable. Spare parts for automation are offered in several states, and suppliers will quote whatever they have unless you say what you accept:

  • New, factory sealed: original packaging, unopened.
  • New, open box or surplus: unused, but packaging opened or the part came from another plant's stores.
  • Refurbished or repaired: used, then inspected, repaired and tested by the supplier or a repair shop.
  • Used, tested: removed from a running machine and function-tested, not refurbished.
  • Exchange: you return your failed unit and pay the difference.

State which conditions you accept, in order of preference. If you accept refurbished, ask what testing was done and what warranty applies.

Certificates and Documents

Ask for documents up front, not after the purchase order. Typical requirements are a certificate of conformity, a test report for refurbished or repaired units, proof of origin or traceability to the manufacturer or an authorised channel, and the declaration of conformity where the part must carry CE marking. For safety-related components, say so in the RFQ: it changes who can quote. Our checklist on how to verify industrial spare parts suppliers covers counterfeit checks for the documents you receive.

Deadline and Delivery Terms

Give a quote deadline with a date and time zone, and separately the date by which the part must be on site. Add the delivery address and the incoterm you expect. "ASAP" is not a deadline; suppliers rank requests with a real date ahead of open-ended ones.

The RFQ Template for Industrial Spare Parts

The template below is the minimum set of fields we recommend for every spare parts RFQ. Copy it into your email, your ERP request or a sourcing platform, and keep the field names identical across suppliers so the answers line up.

FieldWhat to writeExampleWhy it matters
ManufacturerOriginal manufacturer, not the distributorSiemensSeparates original from compatible parts
Part numberFull order code with all suffixes6ES7214-1AG40-0XB0Short codes produce quotes for the wrong variant
Revision / firmwareHardware version and firmware you runFirmware V4.x, matches backup projectAvoids a part that will not accept your program
DescriptionPlain text, one lineS7-1200 CPU 1214C DC/DC/DCLets the supplier spot a typo in the code
QuantityUnits now, plus expected annual need if known2 now, more likely next yearAffects price breaks and stock allocation
Condition acceptedIn order of preferenceNew sealed; new surplus; refurbished with warrantyMakes quotes comparable
AlternativesSuccessor or equivalent accepted or notSuccessor accepted if pin-compatibleOpens more offers for obsolete parts
DocumentsCertificates and reports requiredCoC; test report for refurbishedAvoids rejecting a part at goods receipt
WarrantyMinimum you acceptState your minimum in monthsTurns a cheap quote into a comparable one
DeliveryAddress, incoterm, required on-site datePlant address, DAP, required dateLead time means nothing without it
Quote deadlineDate, time and time zoneDate, 12:00 CETSets a fair, common cut-off
Response formatThe columns you want backUnit price, currency, lead time in days, condition, warranty, validityRemoves manual reformatting

Asking suppliers to answer in the same columns is what makes comparison fast.

Step 3: Decide How Many Suppliers to Ask

Send each RFQ to enough qualified suppliers to see the market, and no more than you can evaluate properly. The right number depends on the part, not on a fixed rule.

  • Current, catalogue parts: two or three suppliers you already trust usually cover it. The OEM or its authorised distributor sets the reference price.
  • Discontinued or hard-to-find parts: widen the search. Surplus dealers, refurbishers and repair shops each hold different stock, so a broader request finds units a short list would miss.
  • Critical spares for a line-down situation: ask more suppliers in parallel and accept a shorter quote window, then verify the winner more carefully, because urgency is when counterfeit and mis-described parts slip through.

Target by brand and product type; suppliers who do not carry the category only send "not available" replies. Keeping two or three reliable sources per critical category is also basic resilience; see how to diversify your industrial supplier base.

OEM RFQ Management

When the OEM or machine builder is one of the bidders, manage that request differently. OEMs often quote list price with a long lead time for legacy parts, or offer only the successor or a repair exchange. Send them the same template, but read their answer as a benchmark for new, warranted parts rather than as the only option.

Step 4: Send the RFQ and Manage Questions Once

Send the same RFQ to every supplier at the same time, and answer every clarification question to all of them. If one supplier learns that refurbished is acceptable and the others do not, you will compare a refurbished price against new prices and draw the wrong conclusion.

Keep the request in one place rather than in separate email threads. A shared RFQ board does this by design: you post the request once, suppliers quote against the same fields, and questions and answers stay attached to the request. On Automa.Net's Request Board a posted RFQ reaches the platform's network of more than 750 verified suppliers, which matters most for parts your usual distributors no longer stock.

Do not extend the deadline for one late supplier unless you extend it for everyone.

Step 5: Compare Quotes Like-for-Like

Procurement team collaborating around table with multiple laptops and printed supplier quotes, comparing bid data and specifications with focused attention

Comparing quotes like-for-like means converting every offer to the same condition, warranty, delivery terms, currency and lead time basis before you look at price. The lowest unit price is often not the lowest cost once these differences are priced in.

Quote fieldHow quotes differHow to normalise
ConditionNew, surplus, refurbished, usedCompare within one condition, or price the risk of the lower one explicitly
Lead time"In stock", "2-3 weeks", "ex works" dateConvert to a date on your site, including transit
Delivery termsEXW, FCA, DAP, with or without freightAdd freight, duties and handling to reach a landed cost
CurrencyEUR, GBP, PLN, USDConvert at one rate, on one day, for all quotes
WarrantyNone to twelve months or moreTreat no warranty as a cost if the part is critical
DocumentsIncluded, on request, not availableExclude quotes that cannot supply what Step 2 required
Minimum orderSingle unit or pack quantityCompare the total for the quantity you actually need
Quote validityDays to weeksCheck the quote is still valid on your award date
Payment termsPrepayment, net termsPrepayment to an unverified supplier is a risk, not just a cash cost

Then weigh price against lead time and risk. For a part that stops a line, every day of lead time has a cost; our guide on unplanned downtime cost shows how to put a number on it. For parts bought repeatedly, compare on total cost of ownership rather than unit price. A supplier who quotes two weeks and routinely delivers in four is more expensive than the quote shows, which is why lead time variability belongs in the comparison.

Step 6: Award, Record and Close the Loop

Award the order, tell the other suppliers they did not win and why in one line, and record the result against the material number. Price, lead time, condition, supplier and date are the minimum. The next time the same part fails, you start from a known price and a known source instead of from zero.

Feedback improves the next round: a supplier who learns they lost on lead time quotes differently next time. Over a year, these records show which suppliers quote accurately and deliver on time.

How to Reduce Manual RFQ Creation Time

The best way to reduce manual RFQ creation time in industrial procurement is to stop writing requests from scratch: generate them from clean material master data, batch them, and let quotes come back in a fixed format. An RFQ engine is the software that does this, turning a list of parts into requests, distributing them to suppliers and collecting structured answers.

  • Pre-fill from the material master. If part number, manufacturer, revision and preferred condition already sit in the master record, the RFQ writes itself. This is why data quality comes before automation.
  • Batch by BOM or by brand. One request covering every Siemens line on a shutdown list is faster for you and for the supplier than ten separate emails.
  • Use structured responses. A spreadsheet or portal with fixed columns removes the copy-paste step between supplier emails and your comparison.
  • Connect it to the ERP. Pushing RFQ and order events into your ERP avoids re-keying; see how webhooks for RFQs and orders work.
  • Start from prices you already know. Knowing the current market range before the RFQ goes out tells you whether a quote is reasonable. Automa.Net's procurement price intelligence reads your material master against more than 36 million live offers to give you that range.

Automation does not fix a vague request: software that sends an incomplete RFQ to more suppliers only produces follow-up questions faster.

RFQ Checklist Before You Hit Send

  • Order code complete: full part number with every suffix, checked against the nameplate.
  • Revision and firmware stated where the replacement must run an existing program.
  • Condition defined: accepted conditions listed in order of preference.
  • Alternatives decided: successor or equivalent accepted or not, in writing.
  • Quantity realistic: current need, plus expected follow-on demand if it changes pricing.
  • Documents listed: certificates, test reports, traceability, declaration of conformity.
  • Two dates given: quote deadline with time zone, and required on-site date.
  • Delivery terms set: address and incoterm.
  • Response format attached: the columns you want back.
  • Supplier list targeted: only suppliers who carry the brand and category, verified before award.

Frequently Asked Questions

What is the RFQ process step by step?

Identify the exact part, write an RFQ with part number, revision, condition, quantity, documents and deadline, choose suppliers who carry that category, send the same request to all of them, compare quotes after normalising condition, lead time and delivery terms, then award and record the result.

How do you streamline electronics RFQ workflows?

Use one template for every request, identify parts down to the full order code and firmware before sending, and require suppliers to answer in fixed columns. Keep questions and answers in one place so all suppliers get the same information, and record each award against the material number so the next RFQ starts from known prices and sources.

What should an RFQ for spare parts include?

Manufacturer, full part number, hardware revision and firmware, quantity, accepted condition, whether a successor is acceptable, required certificates and test reports, warranty, delivery address and incoterm, required on-site date, quote deadline and the response format. Missing any of these usually costs an extra round of emails.

How many suppliers should you send an RFQ to?

For current catalogue parts, two or three trusted suppliers usually show the market. For obsolete or hard-to-find parts, widen the request to surplus dealers, refurbishers and repair shops, because each holds different stock. Only send to suppliers who carry the brand and category.

How do you automate the RFQ process?

Generate requests from clean material master data, batch parts by BOM or brand, collect answers in a structured portal or spreadsheet, and connect RFQ and order events to your ERP. Automation speeds up a good request; it does not repair an incomplete one.

What is an RFQ engine?

An RFQ engine is software that turns a list of parts into quotation requests, distributes them to selected suppliers and collects their answers in a structured, comparable format. It replaces manual email and spreadsheet consolidation, and the better ones also keep the history of prices and suppliers per part.